This project consist of detention areas distributed throughout various sites in the upper areas of the Ward Creek watershed. These detention sites are green spaces that will provide extra storage for stormwater during peak runoff times and assist with flood risk reduction. A total of 200 acres will be utilized and will take approximately 3 years to complete at a cost of $30.7M
Potential Locations of Detention Sites